Dockers 501 Jeans
May 1 estimated inventory 670 1,660
May 31 desired inventory 420 1,860
Assume the following direct labor data per 10 pairs of Dockers and 501 Jeans for four different sewing operations:

Direct Labor per 10 Pairs
Dockers 501 Jeans
Inseam 18 minutes 9 minutes
Outerseam 20 14
Pockets 6 9
Zipper 12 6
Total 56 minutes 38 minutes
a. Prepare a production budget for May. Prepare the budget in two columns: Dockers® and 501 Jeans®.
b. Prepare the May direct labor cost budget for the four sewing operations, assuming a $13 wage per hour for the inseam and outerseam sewing operations and a $15 wage per hour for the pocket and zipper sewing operations. Prepare the direct labor cost budget in four columns: inseam, outerseam, pockets, and zipper.
Answer:

a. LEVI STRAUSS & CO.
Production Budget
May 2014
(assumed data)
Dockers® 501 Jeans®
Expected units to be sold 23,600 53,100
Plus May 31 desired inventory 420 1,860
Total units 24,020 54,960
Less May 1 estimated inventory 670 1,660
Total units to be produced 23,350 53,300
b. LEVI STRAUSS & CO.
Direct Labor Cost Budget
May 2014
(assumed data)
Inseam
Outerseam
Pockets Zipper Total
Dockers® 42,030 1 46,700 2 14,010 3 28,020 4
501 Jeans® 47,970 5 74,620 6 47,9707 31,980 8
Total minutes 90,000 121,320 61,980 60,000
Total direct labor hours
(÷ 60 minutes) 1,500 2,022 1,033 1,000
× Direct labor rate × $13 × $13 × $15 × $15
Total direct labor cost $19,500 $26,286 $15,495 $15,000 $76,281
1 (23,350 ÷ 10 pairs) × 18 min. = 42,030 min.
2 (23,350 ÷ 10 pairs) × 20 min. = 46,700 min.
3 (23,350 ÷ 10 pairs) × 6 min. = 14,010 min.
4 (23,350 ÷ 10 pairs) × 12 min. = 28,020 min.
5 (53,300 ÷ 10 pairs) × 9 min. = 47,970 min.
6 (53,300 ÷ 10 pairs) × 14 min. = 74,620 min.
7 (53,300 ÷ 10 pairs) × 9 min. = 47,970 min.
8 (53,300 ÷ 10 pairs) × 6 min. = 31,980 min.