The Rolling Department of Keystone Steel Company had 400 tons in beginning work in process inventory (20% complete
The Rolling Department of Keystone Steel Company had 400 tons in beginning work in process inventory (20% complete). During the period, 7,900 tons were completed. The ending work in process inventory was 1,000 tons (30% complete). What are the total equivalent units for conversion costs?
Answer:
Percent Total Conversion Equivalent Whole Completed Units for Units in Period Conversion Inventory in process, beginning of period……………… 400 80% 320 Started and completed during the period……………… 7,500* 100% 7,500 Transferred out of Rolling (completed)………………… 7,900 7,820 Inventory in process, end of period……………………… 1,000 30% 300 Total units to be assigned costs………………………… 8,900 8,120 * 7,900 – 400